Everything you need to know about U.S. 27 road construction

Screen Shot 2019-02-21 at 12.19.18 PM

The goal of the project is to rework U.S. 27 from Interstate 24 to the Olgiati Bridge to create a straighter path with new traffic lanes. (Photo: TDOT)

Table of Contents

If you drive around downtown Chattanooga much, you’re probably already aware that U.S. Highway 27 is under construction. But it may not be clear exactly what’s happening with the multi-million-dollar project, so we’re here to break it down for you.

Currently, the main concentration on the project is bridge work, and most of it is taking place on the substructures beneath the bridges on U.S. 27 throughout the project area.

The goal of the project is to rework U.S. 27 from Interstate 24 to the Olgiati Bridge to create a straighter path with new traffic lanes.

Let’s start with some fast facts.

🚧 Total area affected = 2.288 miles

🚧 Total project cost = $143 million

🚧 It’s funded with state + federal funds — 80% federal, 20% state.

🚧 Dement Construction Company LLC won the contract for the project in December 2015 slated to be completed in January 2020.

Why the change?

The changes affect a part of the road that was built in the 1950s + ‘60s, Tennessee Department of Transportation spokeswoman Jennifer Flynn said via email.

“Reconstruction is needed to address safety and capacity issues to better serve the nearly 70,000 vehicles that travel this route every day,” she said.

Project highlights

  • Crews are modifying the interchanges at West Main Street, Martin Luther King Boulevard + East 4th Street.
  • The project includes the addition of a collector-distributor road on U.S. 27 South to improve access to 4th Street, 6th Street and Martin Luther King Boulevard.
  • There will also be a dedicated ramp to 4th Street on U.S. 27 North and a dedicated ramp from Martin Luther King Boulevard to U.S. 27 North

What are the phases of the project?

There are four phases and we’re in phase three, so you’re probably already seeing some of the above-mentioned changes.

Phase three consists of:

  • Traffic shifted, southbound bridge work underway
  • Construction of the new 4th Street overpass and ramps continues
  • Construction of the new MLK interchange ramps continue
  • Reconstruction of the city streets under U.S. 27 underway
  • Olgiati Bridge widening continues

Phase four consists of:

More from NOOGAtoday
We take a look back in time as the Scenic City gears up for another busy shopping season.
Miller Park is about to become a winter wonderland.
‘Tis the season for giving back, and we’ve got lots of ways to do it.
Southside’s 24-hour festival, MAINx24, will take place on Saturday, Dec. 6 this year. Here’s the need-to-know-info.
From luxury treehouses to cozy cottages, Chattanooga is full of special places to stay that offer guests a break from traditional motels and hotels.
Thanksgiving season is here — fill your plate with community and gratitude.
Spoiler alert: It’s not great. We dove into the Texas A&M Transportation Institute’s congestion data so you don’t have to.
Check out some dine-in and carry-out options for Thanksgiving dinner this year.
New vehicle detection technology is expected to help traffic flow more smoothly and improve safety across the city.
Over the next 10 days, we’re launching a reader-driven campaign to sustain what we do best.